Recent Topic

10/recent/ticker-posts

About Me

Award Passed On Consent Cannot Be Held To Be Patently Illegal Or Contrary To Public Policy: Himachal Pradesh HC

 

Himachal Pradesh High Court Upholds Consent-Based Arbitral Award

In a significant judgment, the Himachal Pradesh High Court, comprising Justices Tarlok Singh Chauhan and Satyen Vaidya, reaffirmed the principle that an arbitral award based on mutual consent cannot be deemed patently illegal or in conflict with the public policy of India.

Background of the Case

The dispute originated from a contract awarded to the respondent for the construction of the Lift Water Supply Scheme (LWSS) "Shri Naina Devi Ji," which included the execution and supply of materials. The contract, dated July 30, 2009, stipulated a completion period of one year, setting the deadline for August 13, 2010. However, delays in handing over the complete site to the contractor impeded timely completion. The appellant, representing the state authorities, sought to forfeit the performance bond due to the non-execution of work, prompting the respondent to seek legal recourse. This intervention led to the appointment of an arbitrator to resolve the dispute.

Arbitral Proceedings and Award

Upon reviewing the case, the arbitrator acknowledged the delays in providing the site to the contractor, which hindered the project's progress. Consequently, the arbitrator awarded the respondent a sum of ₹57,45,832 under Claim No.1 for escalation costs, while rejecting other claims presented by the respondent. The award was primarily based on the admissions and assent of the appellant regarding the delay and the consequent escalation claim.

Challenge Under Section 34

Dissatisfied with the arbitral award, the appellant filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, challenging its validity. The primary contention was that the award was patently illegal and in conflict with the public policy of India. However, the learned Single Judge observed that the award was largely consensual, with the appellant admitting to the delays and the resultant escalation costs. Given these admissions, the Single Judge dismissed the appellant's challenge on July 6, 2023.

Appeal Under Section 37

Undeterred, the appellant appealed under Section 37(1)(c) of the Act, seeking to overturn the Single Judge's decision. The appellant reiterated arguments of patent illegality and contravention of public policy. The Division Bench, however, emphasized the limited scope of judicial intervention in arbitral matters, particularly when the award is based on mutual consent and admissions by the parties involved.

Court's Analysis and Conclusion

The High Court referred to the Supreme Court's judgment in Punjab State Civil Supplies Corporation Limited & Anr. vs. M/s Sanman Rice Mills & Ors., which underscored the restricted scope of court intervention in arbitral awards, confined to grounds explicitly stated in Section 34 of the Act. The appellate jurisdiction under Section 37 is similarly constrained, focusing on whether the lower court's decision aligns with the parameters set forth in Section 34.

In this context, the High Court noted that the arbitral award was a result of mutual consent, with the appellant acknowledging the delays and the legitimacy of the escalation claim. Such consensual awards, the court held, do not meet the threshold for being considered patently illegal or contrary to public policy. Consequently, the court dismissed the appeal, upholding the arbitral award and the Single Judge's order.

Implications of the Judgment

This judgment reinforces the sanctity of consensual arbitral awards and underscores the judiciary's limited role in interfering with such awards. It affirms that when parties mutually agree on terms during arbitration, subsequent challenges on grounds of patent illegality or public policy are unlikely to succeed unless there is a clear violation of statutory provisions or fundamental legal principles.

The decision also highlights the importance of timely site handovers in construction contracts and the potential financial implications of delays. Contracting parties are reminded of the necessity to adhere to agreed timelines and the consequences of failing to do so, which may include liability for escalation costs and other damages.

Conclusion

The Himachal Pradesh High Court's ruling serves as a precedent for upholding arbitral awards derived from mutual consent, limiting the scope for challenges based on alleged illegality or public policy conflicts. It emphasizes the judiciary's deference to the arbitral process and the agreements reached by parties within that framework, thereby promoting the efficacy and finality of arbitration as a means of dispute resolution.

Court Practice Community

WhatsApp Group Invite

Join WhatsApp Community



Post a Comment

0 Comments

'; (function() { var dsq = document.createElement('script'); dsq.type = 'text/javascript'; dsq.async = true; dsq.src = '//' + disqus_shortname + '.disqus.com/embed.js'; (document.getElementsByTagName('head')[0] || document.getElementsByTagName('body')[0]).appendChild(dsq); })();