The Bombay High Court held that compensation determined in proceedings under Section 28A of the Land Acquisition Act cannot be restricted solely to the compensation amount awarded in the foundational award relied upon for redetermination. The Court observed that Section 28A is a beneficial provision enacted to eliminate inequality in compensation among landowners whose lands are acquired under the same notification. Because of the remedial nature of this provision, the power of redetermination must not be narrowly interpreted in a way that limits compensation strictly to the amount fixed in the foundational award.
The decision was delivered by Justice Shailesh P. Brahme while hearing a batch of first appeals filed by several landowners who had challenged the judgments of the Reference Court. The Reference Court had rejected their claims seeking enhanced compensation through proceedings under Section 28A of the Land Acquisition Act. The appeals were filed by landowners whose properties had been acquired under a notification issued for a public purpose under Section 4 of the Land Acquisition Act.
The dispute arose from the acquisition of lands under a notification issued in December 1986. Following the notification, the Special Land Acquisition Officer passed the original award determining the compensation payable to the landowners. However, in that award the officer did not grant compensation for wells, trees, or structures that were present on the acquired lands. Some landowners subsequently sought reference proceedings under Section 18 of the Land Acquisition Act, and in those proceedings the Reference Court enhanced the compensation awarded for the acquired lands.
This enhanced award later came to be treated as the foundational award for the purpose of redetermination under Section 28A of the Land Acquisition Act. Section 28A allows landowners who did not initially seek a reference under Section 18 to apply for redetermination of compensation on the basis of a higher award passed in another reference arising from the same acquisition notification. The appellants in the present case were landowners who had not filed references under Section 18 earlier. After the enhanced award was delivered in the separate reference proceeding, they submitted applications under Section 28A seeking redetermination of their compensation on the basis of that award.
The Reference Court, however, rejected their claims. It held that the compensation payable under Section 28A could not exceed the amount awarded in the foundational award relied upon by the applicants. On this reasoning, the Reference Court declined to grant the enhanced compensation sought by the appellants. Aggrieved by this decision, the landowners approached the High Court through first appeals.
While examining the appeals, the High Court undertook a detailed analysis of the legislative scheme and purpose of Section 28A of the Land Acquisition Act. The Court noted that the provision was introduced to ensure fairness among landowners whose lands are acquired under the same notification. Before the introduction of Section 28A, only those landowners who had filed references under Section 18 could benefit from enhanced compensation awarded by courts. This situation created disparities because landowners who were unaware of their legal rights or lacked the means to pursue legal remedies could not obtain similar benefits.
The Court observed that Section 28A was introduced as a remedial and beneficial provision designed to remove such inequalities. The objective of the provision is to ensure that similarly situated landowners receive comparable compensation when their lands are acquired through the same acquisition proceedings. Therefore, the interpretation of Section 28A must reflect its beneficial purpose and must not defeat the objective of providing fair compensation to landowners who had earlier failed to seek reference.
The High Court clarified that the claimants seeking redetermination under Section 28A are entitled to compensation at the same rate as determined in the foundational award. However, the Court explained that this does not mean that compensation must always be confined strictly to the amount mentioned in that award in all circumstances. The Court observed that earlier judicial precedents relied upon by the Reference Court did not impose an absolute prohibition against awarding compensation beyond what was stated in the foundational award.
The Court explained that while the market value determined in the foundational award serves as a benchmark for redetermination, the compensation awarded under Section 28A cannot be restricted in a rigid or mechanical manner. The provision allows courts to consider additional components of compensation where justified by the material on record. This interpretation ensures that the remedial purpose of the provision is fulfilled.
After examining the material on record, the High Court found that the appellants were entitled to receive compensation at the same rate as that fixed in the foundational award. The Court held that the appropriate compensation would be calculated at the rate of Rs. 1500 per Are for dry land and Rs. 3000 per Are for irrigated land. These rates corresponded to the rates determined in the foundational award that served as the basis for the redetermination claims.
The Court observed that the Reference Court had committed a manifest illegality by denying the appellants compensation at these rates despite the existence of the foundational award establishing the market value. The High Court noted that the appellants had been unjustly deprived of compensation to which they were legally entitled under Section 28A.
The Court further clarified that in appropriate cases additional compensation may also be awarded if credible evidence demonstrates that certain elements of compensation were wrongly denied in the earlier proceedings. For instance, if the material on record establishes that the acquired lands were irrigated or that compensation for wells, trees, or structures had been arbitrarily omitted, the Court has the authority to grant such additional compensation.
Applying these principles to the present case, the High Court partly allowed certain appeals in which the evidence indicated that the acquired lands were irrigated. The Court recognized that the nature of the land is an important factor in determining the amount of compensation because irrigated lands generally command higher market value than dry lands.
Through this judgment, the High Court reiterated that Section 28A of the Land Acquisition Act must be interpreted in a manner that advances its beneficial objective. The provision exists to ensure that landowners who were unable to pursue earlier legal remedies are not placed at a disadvantage compared to those who sought reference proceedings. By allowing redetermination of compensation on the basis of a higher award passed in a similar case, the law aims to ensure uniformity and fairness in compensation for land acquisition.
The Court emphasized that the interpretation adopted by the Reference Court would undermine this objective by imposing an unduly restrictive approach to redetermination proceedings. If compensation were rigidly limited in all circumstances to the exact amount specified in the foundational award, it would defeat the remedial purpose of Section 28A and perpetuate inequality among landowners affected by the same acquisition notification.
Accordingly, the High Court held that compensation determined in redetermination proceedings cannot be restricted solely to the amount stated in the foundational award and that courts must consider the broader scheme and purpose of the law while determining compensation. By partly allowing the appeals and correcting the errors committed by the Reference Court, the High Court ensured that the landowners received compensation consistent with the legal principles governing redetermination under the Land Acquisition Act.

0 Comments
Thank you for your response. It will help us to improve in the future.